The latest news from Alpha Omega Power.
Samsung SDI America will supply 1 GWh of its SBB 1.7 energy storage solution to AOP, bringing total supply agreements to 1.5 GWh. All cells and modules will be made at the StarPlus Energy plant in Kokomo, Indiana, for AOP projects in the WECC and ERCOT markets.

AOP and Fengate closed a tax equity capital commitment with First Citizens Bank and East West Bank on the 200 MW / 400 MWh Vertus Energy Storage Project in Galveston County, Texas, currently under construction.
-p-800.jpg)
The Caballero BESS facility became fully operational on April 1, 2025. AOP hosted a community open house and donated $7,500 to local organizations including STEM scholarships and the 5 Cities Homeless Coalition.

The 100 MW / 400 MWh Caballero BESS in Nipomo, California achieved full commercial operations — the first facility of its kind in San Luis Obispo County, providing enough clean energy to power 100,000+ homes for up to four hours.

Fengate and AOP achieved financial close on the Caballero BESS, a 400 MWh battery storage project in California, with financing from MUFG Bank and U.S. Bancorp Impact Finance.

Fengate Asset Management partnered with Alpha Omega Power to build a leading BESS developer and independent power producer platform focused on utility-scale standalone battery storage projects.